Rehearing denied Caterbury man challenging NHPUC on what it requires PSNH charge to extend service

Click headline or here to open angled item
Though we recognize that the cost of Mr. Snyder’s line extension is significant given the length of public road currently without electric service, we cannot conclude that it would be fairer for other customers to subsidize Mr. Snyder’s decision to build o a parcel that has no electric service.