Eversource hikes cost of Laconia project after alleged deadline change


LACONIA — The state’s largest utility has raised the price of burying power lines in the Lakeside Avenue project because the city said it needed the work finished by this month, not by May as was originally planned.

“On January 23 we were told that the city wanted to expedite the project and complete our work by March 15,” said Eversource spokesman Kaitlyn Woods. “We had to get additional estimates from outside sources in order to meet the expedited timeline.”

That was news to Mayor Ed Engler.

“That’s the first I’ve heard that,” said Engler when reached in his office at the Laconia Daily Sun.

The City Council will hear the explanation for the cost overrun directly from Eversource officials at a special meeting on Thursday night.

The $2.6 million Lakeside Avenue project, which is aimed at enhancing the Weirs Beach roads and sidewalks, includes an “aesthetics” program of enhancements aimed at improving the views for visitors. Part of that program buries power lines through the area, which would eliminate unsightly utility poles.

The project began last year and is nearing completion. The city plans to have it completed by May or early June, city officials said, in time for summer visitors and Motorcycle Week.

Engler said Eversource initially estimated the cost of designing and constructing its part of the project at $311,316. The new underground sections have been built and about three-quarters of the work of pulling the cables by Eversource and two other utilities has been done, he said.

But Woods said Eversource was told the city wanted the burying of lines to be done sooner. The company had planned to do the work with its own workers, but after getting “the expedited timeline” from Laconia it put the work out to bid to subcontractors.

The new timeline would mean the work was more expensive, she said. The utility informed the city that the cost would not exceed $786,000.

“That’s more than double the cost of their (original) estimate,” Engler said. “It just doesn’t make any sense.”

Asked a second time if the city had told its partners in the project that the timeline had been expedited, Engler said it had not.

“That’s the first we’ve heard of this,” he said.

Engler was also asked what the city would do if the utility stands by its cost increase.

“All we were told (by Eversource) was that they had badly underestimated in the original estimate,” he said. “What we’ll do going forward will depend on what happens next. It just doesn’t make sense that the council would be told about this when the project is about 70 percent complete.”


Comments


To improve the chance of seeing your comment posted here or published in the New Hampshire Union Leader:

  • Identify yourself. Accounts using fake or incomplete names are suspended regardless of the quality of posts.
  • Say something new, stay on topic, keep it short.
  • Links to outside URLs are discouraged, if used they should be on topic.
  • Avoid comments in bad taste, write well, avoid using all capital letters
  • Don't cite facts about individuals or businesses without providing a means to verify the claim
  • If you see an objectionable comment please click the "Report Abuse" button and be sure to tell us why.

Note: Comments are the opinion of the respective poster and not of the publisher.

Paul Conboy said Monday, March 20, 2017 at 9:31 am

The project is 70% complete and now [ Big Surprise ] e$ource has invented an excuse for more than doubling the cost of their bid. We haven't heard that one since their last project - the scrubber doubled in cost. Oops! Ratepayers and taxpayers take it on the chin again. Wait until they double the cost of no pass and the price of power in New Hampshire and New England goes out of reach for good. This level of incompetence is never tolerated in the real world. God help us.

REPORT ABUSE

Barry Doucette said Monday, March 20, 2017 at 9:47 am

Being a monopoly has many benefits. Blackmailing a city is one of them. Some contractors do it all the time and Eversource is continually increasing their prices with no improvement of service or delivery. Solar is looking better every day...

REPORT ABUSE

ROBERT J DALY said Monday, March 20, 2017 at 9:48 am

From what I read, and time is money, Eversource was told by the city to speed up the project, causing them to revise estimates to get the project done more quickly. OK, that makes sense. And this is the first that the mayor has heard of it? So who authorized the speedup of the project? There must be more to this story.

REPORT ABUSE

PAUL LUNDWALL said Monday, March 20, 2017 at 2:30 pm

Just keep passing it on to the costumers. NH is number four in the continental United States for highest rates surely Eversource is pushing hard to place us at the top of that list. We had two rate hikes last summer, what's a few more.

REPORT ABUSE

ann guinard said Monday, March 20, 2017 at 3:55 pm

Have Eversource tell who gave them the okay and get it in writing. Something is wrong with this story.

REPORT ABUSE

Post a comment


You must sign in before you can post comments. If you are experiencing issues with your account please e-mail abuse@unionleader.com.




NH Maple Weekend NH Maple Weekend
All Weekend

Sap Gathering Contest Sap Gathering Contest
Saturday, 10 a.m.

45th Annual NH Camping and RV Show 45th Annual NH Camping and RV Show
Friday, 1-8 p.m.,
Saturday, 10 a.m. - 8 p.m.,
Sunday, 10 a.m. - 5 p.m.

Ales for Tails Ales for Tails
Sunday, 1-5 p.m.